Schedule Planning and Network Analysis

It seems that we didn’t update our portfolio for quite a period of time due to the mid semester test and 3 weeks of holiday. Oh my goodness, so enjoy….Hooray!!!
Wait wait wait……is there some things that we have missed up???!! Oh…our Tutorial 4 assignment!!

We are requested to create a schedule for our project using Microsoft Project 2007 based on the derived WBS and also perform a network analysis (AON) with a stated assumption using Microsoft Visio. The lucky thing is we are still remembered how to use the Microsoft Project and Visio after a long break, and finally come out with the “answer” as per below:-
WBS of the Inventory Tracking System

Inventory Tracking System Project Plan

AON for Inventory Tracking Sytem Project
Summary:
Earliest Finish Time: 82 days
Latest Finish Time: 85 days
Float: 3 days
Critical Path: A-B-C-D-F-G-H-K-L

We spent our time for meeting up on weekend and weekday and always out of mind and want to give up, nevertheless, each day brings its own bread. We have finished and can submit it on time. Time flies as swiftly as an arrow, we will be facing you (our LOVELY lecturer) soon…..Oh…words can hardly describe how “xxx” we are..Haha….. :)